Woodcrest utility project design contract amendment was scheduled for a March 4 council vote

Ahead of its March 4, 2025 meeting, Bothell's agenda asked the council to approve a $244,042 amendment to Stantec's design contract for the Woodcrest Neighborhood Utility Project, raising the total to $1,215,300.15 1.

What the records say

In materials published ahead of the March 4, 2025 meeting, Bothell's agenda included Agenda Bill 25-031, which asked the council to approve a resolution authorizing the City Manager to sign Amendment No. 1 to a Professional Services Agreement with Stantec Consultants 1. The amendment would add $244,042, bringing the contract total to $1,215,300.15 for consultant design services on the Woodcrest Neighborhood Utility Project 1. The item was listed on the consent agenda, meaning it would pass with a single motion and vote unless a councilmember pulled it for separate discussion 1. The city's own 2025-26 legislative agenda describes the Woodcrest neighborhood as 157 manufactured and mobile homes providing affordable housing to senior and fixed-income residents, with substandard, failure-prone utility systems including undersized water mains, sewer infiltration, and poorly functioning surface water facilities 1. The available records do not establish the meeting's outcome.

  • Agenda Bill 25-031 asked the council to approve a resolution authorizing the City Manager to sign Amendment No. 1 to the Professional Services Agreement with Stantec Consultants 1.
  • The amendment would add $244,042, bringing the contract total to $1,215,300.15 for consultant design services for the Woodcrest Neighborhood Utility Project 1.
  • The item was on the consent agenda, which is passed with a single motion and vote unless the council pulls it for separate discussion 1.
  • The city's legislative agenda describes the Woodcrest neighborhood as 157 manufactured and mobile homes housing senior and fixed-income residents, with undersized water mains, sewer infiltration and inflow, and poorly functioning surface water facilities 1.

Why it matters

The Woodcrest project, estimated by the city at $7.4 million, is intended to update the neighborhood's water, sewer, and stormwater infrastructure to improve water service and fire flow and reduce utility repairs 1. This amendment would increase what the city is spending on design before any construction begins, and the design work is a prerequisite step toward the utility upgrades residents in that neighborhood would eventually see 1.

What changed / what's next

  • The proposed Amendment No. 1 would increase the Stantec design contract by $244,042 to a total of $1,215,300.15 1.
  • The available records do not establish the meeting's outcome, so it is unknown whether the council approved the amendment on March 4, 2025.